Project Overview
20 May 2024
8
AR
TwinTech Tower
Commercial Development
Kuala Lumpur, Malaysia
Project Start
12 Jan 2024
Target Completion
30 Nov 2025
Project Value
RM 320,000,000
26°C
Partly Cloudy
Project Progress
62%
Overall Progress
Planned Progress
68%
Actual Progress
62%
Behind Schedule
6%
Planned
Actual
JanFebMarAprMayJunJulAugSepOctNov
Cost Performance
Budgeted
RM 128.5M
Actual Cost
RM 97.2M
Variance
-RM 31.3M
Cost Perf. Index (CPI)
Under Budget
0.92
1
0
2
Schedule Perf. (SPI)
Behind
0.88
1
0
2
Issues Summary
24
Total
High
8
Medium
7
Low
6
Closed
3
Recent High Priority
View All
- Structural clash at L12 2h ago
- MEP coordination B2 5h ago
3D Model Viewer
Progress Comparison
Floor
Planned
Level 20
(68%)
Actual
Level 15
(62%)
Site Photo
Work Package Progress
Work Package
Planned
Actual
Status
Substructure
100%
100%
Completed
Superstructure
75%
60%
Behind
MEP Works
55%
45%
Behind
Facade Works
30%
20%
Behind
Documents
View AllA-1001_Architectural.pdf
Uploaded by Zainul - 20 May
2.4 MB
S-2001_Structural.pdf
Uploaded by Farah - 19 May
3.1 MB
M-3001_MEP Drawing.pdf
Uploaded by Hadi - 18 May
2.8 MB
Method Statement.pdf
Uploaded by Site Team
1.5 MB
Weather Forecast
Mon
20 May
26°C
18°C
Tue
21 May
27°C
19°C
Wed
22 May
26°C
19°C
Thu
23 May
28°C
20°C
Fri
24 May
27°C
19°C